Dependencies between tasks

Another powerful feature of the Scheduler module is the possibility of adding dependencies to a task. The dependencies are tasks that will be launched just after the parent task finishes. These dependencies can also contain other dependencies, creating a workflow.

Types​

There are two main types of dependencies.

Synchronous dependencies​

The synchronous dependencies are, as their name suggest, executed in a synchronous way, in a configurable order.

The synchronous dependencies are created by setting the Blocking=Yes option.

Setting blocking to yes means that, in case that any of the dependencies ends with an error, it will cancel the entire synchronous execution stack.

To manage the stack, there is the Order criterion, which is used to set the order in which the synchronous dependencies are going to be executed.

Asynchronous dependencies​

The asynchronous dependencies are executed in bulk and their execution order can't be configured.

As the dependencies are executed in bulk, they are not going to block each other

Dependencies configuration​

The dependency configuration screen allows to create two type of dependencies, synchronous and asynchronous.

The difference between them is just that one is blocking whereas the other is not.

In order to add a task as a dependency, its launch type must be set to Manual.

ElementDefinitionUse
TaskThe task the dependency is going to executeRequired
BlockingUsed to define if the dependency is going to be synchronous or asynchronous, and if it can cancel the synchronous dependencies execution stackRequired
OrderSynchronous dependency execution order, only needed if the Blocking option is set to Yes, otherwise it will be disabledRequired

Workflows​

Workflow example

This image shows an example on how to create a workflow using the scheduler dependencies concatenation.

Flow runs and fan-in​

A task that is launched by its schedule, by hand, by a file or by a webhook starts a flow run. The run groups that execution and every dependency launched from it, directly or through other dependencies: these tasks are the scope of the run.

A task with several parents (fan-in) is launched once, not once per parent. The child waits until every parent that is in the scope of the run has ended, and it is launched only if each one met its condition: it ended successfully, or with a warning or an error when the parent launches its dependencies on warning or on error. If any parent did not meet its condition, the child is skipped, and the skip propagates: the children of a skipped task are skipped in turn.

The run ends when no task is waiting or running. Its status is the worst of its executions: error (error, stopped or interrupted), then warning (warning, or any skipped task), then ok.

Parameters of a dependency​

Each parameter of a dependency takes the first value found in this order:

  1. the default value of the task;
  2. the value propagated by the parent that completes the join (the one that ends last);
  3. the run parameter with the same name. Run parameters apply only to VARIABLE parameters: the child defines which parameters it accepts. The run parameters of a webhook are the values mapped from its data, so they reach every step of the flow.

Circular dependencies​

Saving a task whose dependencies would make it launch itself, directly or through other tasks, is rejected with a Circular dependency message. Remove the dependency that closes the loop.

Flow runs screen​

The Flow runs option of the scheduler menu lists the runs, newest first, with their status, root task, root execution, who launched it, and start and end times. Selecting a run shows its executions and the tasks that were skipped. In the task manager, select an execution and press Open run to go straight to its run.